Seattle Subway Project Gets Out of a Hole with Precision Mudslinging by SENNEBOGEN 870 M

Seattle, WA –Mudslinging isn’t the type of activity that normally wins accolades, but Michael Diponio has nothing but praise for the way his SENNEBOGEN 870 M material handler has been heaving the muck around at his current jobsite for Sound Transit in Seattle.

The SENNEBOGEN 870 delivers its payload smoothly over 60 ft. in the air and carefully deposits it in truck.

Sound Transit is extending the U-Link subway from its LRT station at Pine Street to a new station planned at Capitol Hill. Diponio, the Vice President of Michigan-based Jay Dee Contractors, is Project Manager for the Jay Dee/Coluccio/Michels joint venture which will mine the two tunnels, each 21 ft. in diameter and 3,800 ft. long.

Tunneling like this is Jay Dee’s stock-in-trade and the family-owned business has been doing it for more than 45 years. With the U-Link project, however, Diponio faced unique challenges posed by the environmental standards of Washington State and the City of Seattle.

The problem, in a word, is muck. Conveyors from the project’s two tunnel boring machines deliver their tailings in the form of a heavy slurry to the open cut for the future subway station. The slurry arrives about 80 ft. below grade, and Diponio has to move the wet muck up to road level and haul it out to his fill site without compromising the city’s strict standards for protecting its water table and roadways.

Clean-up can be costly
“We’re working in a very urban area here, and our haul route travels directly through a residential area,” Diponio explains. “The track-out is severely limited, and using thousands of gallons of wash water every day is counter-productive.” The contract includes significant cash incentives for complying with these requirements, and a local environmental technician is stationed on the site to monitor the operation. Officials for the city and consultants conduct a walking tour of the project every week.

The simplest approach to moving the muck was with stacking conveyors transferring it up to a muck bin or to waiting dump trucks. However, the conveyor process resulted in the muck splashing too much for crews to clean up. “The drop from the end of the conveyor into the dump was about 6 or 7 feet. The muck was splattering everywhere, 30 or 40 feet. It was going right up our sound wall! We had a ‘splooge patrol’ of 5 guys with loaders going full time to clean up.”

The muck wouldn’t splatter so much if it was drier, of course, but it then becomes too sticky to offload easily from the buckets and dumps. Foaming agents are actually added by the Tunnel Boring Machine to condition the muck so that it flows freely from the excavation chamber.

Precise handling is the solution
“What we needed was a method to place, not drop, the material precisely into the dump trucks. We looked at some other machines, but we needed more horsepower and more mass to get the stability for a precise transfer. We went with the SENNEBOGEN 870 M on the recommendation of Modern Machinery. But really, we had no idea if it was going to work.”

Operator scoops up tailings with custom clamshell.

The SENNEBOGEN 870 M is a purpose-built material handler weighing 165,000 lbs. and powered by a 426 HP engine. The wheeled unit is mounted on a specially reinforced platform raising it 30 feet above the floor of the excavation where the muck flows in. Modern Machinery fitted the machine with a SENNEBOGEN extra-long boom to make the 63 ft. reach up to the waiting trucks. Its 2.5 yard clamshell bucket was also custom-built with tight bucket closing tolerances to prevent leakage and spilling as the clamshell bucket swings over the truck bed.

The SENNEBOGEN is positioned down in the hole, 40 feet beneath the ground surface. Once the bucket is raised above the surface and the machine swings over the edge of the shaft, the machine operator loses sight of the bucket. Jay Dee’s operators scoop up the muck and guide it up to the road level using two cameras to find their way. One camera is mounted at the boom knuckle and another is positioned roadside by the trucks’ station. With a total boom length of 63 ft., they have just 3 inches of clearance to reach their targets, the dump bodies and pup trailers. The bucket is carefully lowered directly into the bed, with only inches of clearance on either side of the bucket, before the bucket is opened to let the muck flow out.

The fleet of dump trains grew as operators became increasingly proficient with the 870 M and the drivers were able to navigate into the exact position with the help of markings painted on the pavement.

Picking up the pace
Loading each truck requires 4 passes to fill the front unit and 5 to fill the trailer. The system was able to get the job done but the question on Diponio’s mind was, how much time would it take? “This method has performed well beyond our expectations,” he’s pleased to say. “We now have eleven trucks moving through the cycle, and the SENNEBOGEN more than keeps up with them.”

Diponio reports that the initial loading times exceeded his target, but the operators advanced up the learning curve very quickly. “Before we started, we spent a day or so with the operators, going over the drawings to make sure everyone understood the concept. The first tests came in at 20 minutes for a full load, and we were looking for 12 minutes,” he recalls. “The average now is under 10 minutes, which means we can now meet our production projections!” The best loading time achieved by any operator so far is just 6 minutes.

The operator carefully positions the bucket over the dump truck and is guided by a camera mounted on the stick.

The contractors are looking forward to earning their bonus for environmental compliance, too. Even at its fastest loading times, the 870 M is moving with precision, enough that the worksite stays meticulously clean. “The inspectors can tour the site in their street shoes without a problem,” claims Diponio. Jay Dee’s “splooge patrol” has been replaced by a crew of two who police the site once a day with a wheelbarrow. A wheel washer system and street sweeper take care of any spillage coming from the trucks’ tailgates.

According to Diponio, the controlled success of the “mudslinging” operation can be credited to the right choice of machine and to SENNEBOGEN’s smooth hydraulics system. “The 870 M is a larger machine than we first considered, but Will Wintermute at Modern Machinery recommended a heavier machine for added stability.” The 870’s hydraulic boom, he says, gives his operators more control over the bucket than a cable crane or excavator would allow.

The speed and precision of the SENNEBOGEN 870 M add a valuable new tool to Jay Dee’s tunneling capabilities. Its clean operation significantly reduces the cost of site maintenance while protecting the quality of ground water. Its fast loading cycles ensure that their haul trucks can keep pace with the tunnel boring machine, which is on track to arrive at Pine Street by the end of this year.

About SENNEBOGEN
SENNEBOGEN has been a leading name in the global material handling industry for nearly 60 years. Based in Stanley, North Carolina, within the greater Charlotte region, SENNEBOGEN LLC offers a complete range of purpose-built machines to suit virtually any material handling application. Established in America in the year 2000, SENNEBOGEN LLC has quickly become a leading provider of specialized equipment solutions for recycling and scrap metal yards, barge and port operations, log-handling, transfer stations and waste facilities from coast to coast. A growing network of distributors supports SENNEBOGEN LLC sales and service across the Americas, ensuring the highest standard of professional machine support and parts availability.

For more information on the full line of SENNEBOGEN green line material handlers, contact:

Constantino Lannes, President
SENNEBOGEN LLC
1957 Sennebogen Trail (formerly 7669 Old Plank Road)
Stanley, NC 28164
Tel: (704) 347-4910 or fax (704) 347-8894
E-mail:
Visit the web site at www.sennebogen-na.com